substation design
Edwards Lane

Client: UK Power Networks

End user: UK Power Networks

Description: Edwards lane C substation overall commissioning

  • Commissioning of the following plant:
  • 2x 132kV earth switches
  • 11kV cable installation
  • Relay panels/AVC/Auto switching/Low Freq panels/battery chargers
Edwards Lane

Client: Clancy Docwra

End user: UK Power Networks

Description: Edwards lane C substation installation

  • Plant installed: 2x 132kV earth switches
  • 6x 132kV wall bushings
  • 132kV Busbars
  • Earthing
  • 11kV cable installation/terminations
  • Relay panels/AVC/Auto switching/Low Freq panels/battery chargers
  • Tele-control panels Multicore cabling