top of page
DJI_0287 Edited.JPG

33/11kV substation -
Turn key project

•Design and Build 33/11kV Substation

•Site built and energised within 5 months

•Piling started 11th February 2022

•Energised on the 1st July 2022

•Civils completed April 2022

•M&E works

•Earthing

•Full testing and commissioning of the 33kV/11kV Substation

DJI_0344.JPG

•Principal Contractor role

•Full civil design

•Full protection and control design

•Full primary design

•Demolish old transformer enclosure

•Removal of transformer and cooler bank

•Design and Build 132/33kV Substation

•Remove old bund and build new one

•M&E works

•Earthing

•Full testing and commissioning of the Substation

Grid Transformer replacement

DJI_0386.JPG

Reinforcement works

•Principal Contractor role

•Principal Designer role

•Full civil design including new access road

and 132kV substation extension

•Full protection and control design

•Full primary design

•132 kV Sealing end platform

•Design and Build 132/33kV Substation

•M&E works

•Protection

•Commissioning

20230203_121817.jpg

•Connection of Electrical Plant

•The supply and installation of the multicore wiring between the Client intake substation and Battery Containers

•The supply and installation of the fiber optic wiring between the Client intake substation and Battery Containers

•The supply and installation of earthing at customer compound

•Supply of DC cables and terminations

•The supply and installation of 33kV cables for client 33kV Switchgear

•Commissioning and testing of all cables

•Commissioning of client switchgear

50MW BESS

DJI_0374.JPG

132kV 50 MW BESS

•132kV ICP works

•Full Electrical Design

•Civil Design

•Full protection and control design

•Full primary design

•M&E works for all HV equipment

•BESS Installation

•132kV cable installation

•Earthing

•Commissioning

bottom of page